One of the large car parks at Swindon’s Great Western Hospital required planing of its existing surface and then laying new SMA 10 wearing course.
Our client required 850m2 of planing and resurfacing works to be carried out with minimal disruption as the hospital remained open 24 hours a day. So, we scheduled the works to be carried out over a weekend. Due to high usage, the car park was in need of updating. We provided various options for our client, and they chose to use Tensar Geogrid in order to prolong the surface.
With our incredible staff and our professional supply chain, we exceeded our clients’ expectations and delivered this project on time and within budget.
Once the new surface was led, new white lining parking bays and directional instructions was applied.
Full scope of works included:
The car park is now designed and built to last for many years, providing patients and visitors with a safer, smoother and more comfortable parking experience.